Junction of Magadi Road-Chord Road

The Project at the Junction of Magadi Road-Chord Road consists
of 530.35 mtr. long underpass with 4 line divided carriage way.
The cost of the project is Rs. 31.86 Crores and is scheduled to
be completed by June 2007.
Road Improvement
Work from HAL corporate office to Kundalahalli
Road Improvement Work from HAL corporate office to Kundalahalli,
a stretch of 5.8 KM at a cost of Rs. 22 crores is in progress.
Road work has been completed and the ROB work is taken up at Marathhalli
by Railways as DC work project. The left carriage way of ROB and
approach road works have been completed and opened for traffic
on 30.03.2007. TOP
Outer Ring
Road work between Mysore Road-Magadi Road

BDA is executing Outer Ring Road work between Mysore Road-Magadi
Road for a length of 5.7 Km-at a cost of Rs. 92 crores. This road
saves about 13 Kms of extra journey to commuters to reach Mysore
Road from Magadi Road (via Kengeri). |